Overbillings and Underbillings Taxes: Why WIP and Returns Differ

Ask a contractor owner what the company earned last year, and you might get two answers. One comes from the reviewed or audited financial statements your surety receives. The other comes from the tax return. Much of the gap often traces back to the WIP schedule, and specifically to how overbillings and underbillings taxes work compared with book accounting.
This confuses owners, lenders, and sometimes even outside accountants. The short version: your WIP schedule adjusts revenue to match progress for financial reporting, but the tax rules for long-term contracts follow their own logic. Depending on your size and method, those two numbers can be close or far apart. This article explains why and what to do about it.
What Overbillings and Underbillings Are
Your WIP schedule compares what you have billed on each job with what you have earned based on progress.
Overbilling (billings in excess of costs and estimated earnings): you have billed more than you have earned. It shows up as a liability on the balance sheet.
Underbilling (costs and estimated earnings in excess of billings): you have earned more than you have billed. It shows up as an asset.
Under GAAP and ASC 606, most commercial contractors recognize revenue over time, usually using a cost-to-cost input measure. The WIP adjustment moves revenue up or down from billings so the income statement reflects earned revenue, not invoiced revenue.
Sureties study these numbers closely. Heavy overbillings can mean strong cash management, or they can hide cash that is already committed to finishing the work. Large underbillings can signal billing delays, unapproved change orders, or profit that may fade.
Overbillings and Underbillings Taxes: Why the Return Differs
Book WIP adjustments for overbillings and underbillings are not always the tax numbers. The tax rules for long-term contracts come from Section 460, and the method you use depends on your size and the contract.
Contractors over the gross receipts test
For 2026, the gross receipts test is average annual gross receipts of $32,000,000 or less over the prior 3 tax years. Contractors over that amount generally must use the percentage of completion method (PCM) for long-term contracts.
Tax PCM also uses a cost-to-cost approach, so the result can look similar to your book WIP. But it is not always identical. The costs that must be allocated to contracts for tax, the treatment of certain indirect costs, and other technical rules can make tax PCM differ from GAAP. Large contractors should still expect a reconciling schedule between book and tax income.
Contractors under the gross receipts test
This is where the gap can be bigger. Under the small contractor exception, a contract is exempt from PCM if you meet the gross receipts test and the contract is expected to be completed within 3 years. OBBBA expanded this from 2 years, effective for contracts entered into in tax years beginning after July 4, 2025.
Exempt contracts can use the completed contract method (CCM), accrual, cash, or other permissible methods. Each one treats overbillings and underbillings differently:
Completed contract method: Income is generally recognized when the job is complete. Overbillings and underbillings on open jobs generally do not affect taxable income until completion.
Accrual method: Income generally follows the all-events test, which often tracks amounts billed and due rather than earned progress.
Cash method: Income is generally recognized when received.
Example
A concrete subcontractor has a $5,000,000 contract with estimated total cost of $4,000,000. At year-end, costs to date are $2,000,000, so the job is 50% complete. Billings to date are $3,000,000.
On the WIP schedule, earned revenue is $2,500,000 ($5,000,000 x 50%). Billings of $3,000,000 exceed that by $500,000, so the books show a $500,000 overbilling. Book gross profit on this job is $500,000 ($2,500,000 earned less $2,000,000 cost).
Now consider taxes, assuming the contract qualifies for the small contractor exception:
Completed contract method: Taxable gross profit from this open job is generally $0 this year. The full profit is recognized when the job is finished.
Accrual method: If $3,000,000 has been billed and is due, taxable income from this job may be based on that billed amount less deductible costs, which could be higher than book profit.
PCM for tax: Revenue would be roughly in line with the $2,500,000 earned figure, subject to tax cost rules.
Same job, same year, very different taxable income. That is why method selection is a planning decision.
Choosing a Tax Method That Fits
The right method depends on your billing patterns and your growth.
If you tend to bill ahead of progress (overbilled), an accrual method based on billings can accelerate taxable income. The completed contract method may defer it, depending on job duration and timing. If you tend to be underbilled, the picture can reverse.
Keep these points in mind:
Method changes need paperwork. Changing accounting methods generally requires Form 3115. Many changes are automatic, but they still must be filed correctly.
Watch the $32,000,000 line. If your 3-year average is near the threshold, plan ahead. Crossing it changes the rules for new contracts. Aggregation rules apply to related businesses, so add up affiliated companies.
Look-back interest comes with PCM. Contracts on PCM are subject to the look-back calculation on Form 8697 after completion. Exempt contracts generally are not.
How This Connects to Your Bonding
Here is the most important point for bonded contractors: tax deferral should not damage the financial statements your surety uses.
Exempt small contractors can use different tax methods than their reviewed or audited financials. That is allowed and common. Your GAAP statements show the WIP schedule with overbillings and underbillings, and your tax return uses the method that fits the tax rules and your facts.
What causes trouble is when an owner tries to shape the books to lower taxes. Pushing revenue out by understating progress, or holding back billings, can make your WIP schedule less reliable. Sureties notice, and it can hurt your bonding capacity. The better approach is clean, accurate GAAP books for the surety and a separate, documented tax method on the return, with a reconciliation that ties the two together.
FAQ
Are overbillings taxable?
It depends on your method. Under tax PCM, income follows cost-to-cost progress, similar to book WIP. Under an accrual method, billed amounts may be taxable when due. Under the completed contract method, income on the job is generally recognized at completion.
Why is my taxable income lower than my book income?
Often because an exempt small contractor uses the completed contract method or another method for tax while the financial statements use GAAP over-time revenue recognition. Other book and tax differences, such as depreciation, also contribute.
Can I use one method for my surety and another for taxes?
Yes, in many cases. Exempt small contractors can use tax methods that differ from their reviewed or audited financial statements. You should keep a clear reconciliation between the two.
Talk to a Contractor Tax Specialist
If your WIP schedule and your tax return never seem to agree, it may be a sign that your method choices are working, or that they need a second look. Payless Taxes works with bonded commercial contractors from $5M to $50M in revenue nationwide on tax planning, tax preparation, and accounting method strategy.
Book a 30-minute call to review your WIP schedule and current tax methods.
This article is general information, not tax or legal advice. Tax rules change and depend on your specific facts. Talk with a qualified tax professional before acting.